UltraTech Cement in Gujarat is seeking a Field Engineer to ensure safe and smooth shutdown/startup of AFBC/CFBC boilers, turbines and auxiliaries, coordinating with shop floor teams. You will identify field abnormalities, report to CCR and Shift Incharge, and optimize field processes while adhering to ABG safety standards.
The role involves managing multiple units in a thermal power plant, handling lignite fuel processes, boiler feed pumps, cooling systems and associated auxiliaries, with
To ensure safe & smooth field operation while start up- shutdown of AFBC and CFBC boiler, turbine and its auxiliaries by Co-ordination with shop floor working agencies. Identify the field abnormalities and report to CCR and Shift Incharge. Ensuring field Process optimization while carrying all TPP field activities, following all safety standards of ABG group.
Job Context : Thermal power plant consists of 1x35 MW and 1x22.5 MW total capacity 57.5MW, condensing type steam turbine with three uncontrolled extractions. Having two boiler Unit-1 CFBC type, multi fuel boiler having steam generation capacity of 170 TPH and Unit-2 AFBC type having steam capacity 110 TPH with working pressure -85 Kg/CM2. The auxiliaries system for steam turbine comprises of HP/LP heaters, high pressure boiler feed pumps having working pressure 95 Kg/CM2, and Air cooled condensers consisting of total 14 Nos. of forced draft fans for 2 units having dia. Of fan-9.5 Mtrs, Steam jet air ejectors, gland steam condensers, 02 Nos of Deaerator system etc. The design fuel for boiler is lignite. The approximate fuel consumption would be 900T/Day considering full load running of all two turbines. The fuel handling plant comprises of two stage screenig -Primary and secondary including hydraulic truck unloaded with various belt conveyors and associated equipments. The lime stone & ash handling system is of pneumatic type. The water treatment system consists of R O & D M plant. Wast water will be treated in waste water treatment plant. Auxiliary cooling water system with induced draft cooling towers and raw and fire water system. There are 08 nos. of screw air compressors with driers for pneumatic as well as instrument air requirement. The field operation of entire TPP field would be a challenge for all engineers with parallel field operation of two units without greed (island mode). Also various fuels may be used in proportions which needs proper skills and continuous field operation with relative processes. Also the Air cooled type condensers is a new technology which needs proper attention for efficient field operation as it is changing with the quality of atmosphere air.
Maintaining maximum economic and quality field work with simultaneously running of both units by carring out regular field activities along with handling field casual manpower.
To ensure safe & smooth field operation while start up- shutdown of AFBC and CFBC boiler, turbine and its auxiliaries by Co-ordination with shop floor working agencies. Identify the field abnormalities and report to CCR and Shift Incharge. Ensuring field Process optimization while carrying all TPP field activities, following all safety standards of ABG group.
Job Context : Thermal power plant consists of 1x35 MW and 1x22.5 MW total capacity 57.5MW, condensing type steam turbine with three uncontrolled extractions. Having two boiler Unit-1 CFBC type, multi fuel boiler having steam generation capacity of 170 TPH and Unit-2 AFBC type having steam capacity 110 TPH with working pressure -85 Kg/CM2. The auxiliaries system for steam turbine comprises of HP/LP heaters, high pressure boiler feed pumps having working pressure 95 Kg/CM2, and Air cooled condensers consisting of total 14 Nos. of forced draft fans for 2 units having dia. Of fan-9.5 Mtrs, Steam jet air ejectors, gland steam condensers, 02 Nos of Deaerator system etc. The design fuel for boiler is lignite. The approximate fuel consumption would be 900T/Day considering full load running of all two turbines. The fuel handling plant comprises of two stage screenig -Primary and secondary including hydraulic truck unloaded with various belt conveyors and associated equipments. The lime stone & ash handling system is of pneumatic type. The water treatment system consists of R O & D M plant. Wast water will be treated in waste water treatment plant. Auxiliary cooling water system with induced draft cooling towers and raw and fire water system. There are 08 nos. of screw air compressors with driers for pneumatic as well as instrument air requirement. The field operation of entire TPP field would be a challenge for all engineers with parallel field operation of two units without greed (island mode). Also various fuels may be used in proportions which needs proper skills and continuous field operation with relative processes. Also the Air cooled type condensers is a new technology which needs proper attention for efficient field operation as it is changing with the quality of atmosphere air.
Maintaining maximum economic and quality field work with simultaneously running of both units by carring out regular field activities along with handling field casual manpower.
Ensure the safe field start up, operation & shutdown to minimise the delay & smooth functioning of both AFBC and CCFBC boilers along with all auxiliaries systems in context of high pressure & temperature processes for fly ash, bed ash and all steam handling equipments.
To maintain house keeping of allotted field area in shift by handling manpower. Also to assist extended operational support to working agencies in doing any job with careful field operations, avoiding wastages of steam, water, fuel, and auxiliary power and optimise the cost of generation.
Ensure no any unsafe work going in Boiler Turbine firld during the shift.